SHED 100'x140'
| Hrs/Qty | Service | Rate/Price | Adjust | Sub Total |
|---|---|---|---|---|
| 5000 Cft | Excavation in foundation of building and other structures including backfilling dressing refilling around structure with excavated earth watering and ramming lead up to 5ft (compacted measurement ), asper drawings, technical provisions and instructions of the Engineer/ Incharge. EXCAVATION |
Rs. 220.00 | 0.00% | Rs. 1,100,000.00 |
| 15000 cf | Supplying / filling local granular material from approved sources with all leads and lifts in or under floor, footing etc. including watering and consolidation by remming in layers not exceeding 9" inch depth leading to full compaction, (compacted measrement), as per drawings, technical provisions and instructions of the Engineer/Incharge. STONE SOILING |
Rs. 250.00 | 0.00% | Rs. 3,750,000.00 |
| 15000 cf | Laying 1:4:8 cement concrete in all types of foundations using specified graded materials including form work, levelling unevenness, compacting, vibrating & curing etc. complete as per drawing, specifications and as directed by the engineer. LEAN |
Rs. 220.00 | 0.00% | Rs. 3,300,000.00 |
| 4 ton | Providing / placing in position steel reinfoecement bars, including cutting, bending, binding (cold twisted or plain) as mentioned in B.O.Q. in position with binding wire etc. in all R.C.C. works at any height and floors, complete as per drawings, specifications and as directed by the engineer. Steel 1/2" |
Rs. 300,000.00 | 0.00% | Rs. 1,200,000.00 |
| 2 ton | Providing / placing in position steel reinfoecement bars, including cutting, bending, binding (cold twisted or plain) as mentioned in B.O.Q. in position with binding wire etc. in all R.C.C. works at any height and floors, complete as per drawings, specifications and as directed by the engineer. Steel 3/8" |
Rs. 380,000.00 | 0.00% | Rs. 760,000.00 |
| 1400 Cft | Providing / laying cement concrete of different mixes as given in B.O.Q. using specified graded materials in columns, beams at floor and level as indicated in B.O.Q. including making 3/4 x 3/4 chanfers at corners of columns, placing of anchor bars for masonary, form work, vibrating, curing, approved plasticiser etc. but excluding the cost of reinforcement complete as per drawings, specifications and as directed by the engineer. REINFORCEMENT CONCRETE |
Rs. 3,200.00 | 0.00% | Rs. 4,480,000.00 |
| 6000 Sqf | Providing / applying weather shield of approved shade in two coats to external faces of walls, columns, beams and where required at any height including scaffolding scrubbing into the surface, curing etc. complete as directed by the engineer |
Rs. 140.00 | 0.00% | Rs. 840,000.00 |
| 14000 Sq | Providing and erection of MS pre fabricated shed as per drawing and design, complete as directed by the engineer. PRE FEB SHADE |
Rs. 2,400.00 | 0.00% | Rs. 33,600,000.00 |
| 14000 Sq | Providing & laying concrete floor with machine mixture upto 4" smooth finish with epoxy floor coat & line marking. 1. concrete floor |
Rs. 750.00 | 0.00% | Rs. 10,500,000.00 |
| 14000 Sq | Roof sheeting profile false ceiling with insulation / underlayment |
Rs. 650.00 | 0.00% | Rs. 9,100,000.00 |
| 1 Job | Doors Main rolling shutter / double leaf door for entry 1 12ft |
Rs. 1,400,000.00 | 0.00% | Rs. 1,400,000.00 |
| 1 Job | Sports equipment (supply & fix) Basketball post (floor mounted or wall-mounted )— set 1 |
Rs. 1,370,000.00 | 0.00% | Rs. 1,370,000.00 |
| 1 Job | Electrical & Lighting LED high-bay / floodlight fixtures for sports |
Rs. 2,900,000.00 | 0.00% | Rs. 2,900,000.00 |
| 0 Sqf | block masonry work, including labor, standard 6"x8"x12" concrete blocks, mortar, Scope of work includes layout, block installation, joint tooling, and site clean-up upon completion. |
Rs. 250.00 | 0.00% | Rs. 0.00 |
| 0 Sq | Plastering work, including labor, surface preparation, application of base and finish coats, and all necessary materials (cement, sand, bonding agents, and additives as required). Work will be completed to a smooth, uniform finish as per project specifications, with clean-up upon completion. |
Rs. 350.00 | 0.00% | Rs. 0.00 |
| 0 nos | UPVC door with frame size 3 x 7 in 6 rooms & 2 no washrooms |
Rs. 30,000.00 | 0.00% | Rs. 0.00 |
| 0 nos | UPVC Windows szie 4 x 4 in 6 rooms & 2 no washrooms |
Rs. 20,000.00 | 0.00% | Rs. 0.00 |
| 0 nos | Player benches / substitutes seating |
Rs. 40,000.00 | 0.00% | Rs. 0.00 |
| 00 Sqf | Stage with non-Skite tiles on top. |
Rs. 800.00 | 0.00% | Rs. 0.00 |
| 0 nos | Washroom complete with tiles upto 7ft including 2 nos WC, 1 nos Commode & 1 washbasin with all accessories. |
Rs. 1,500,000.00 | 0.00% | Rs. 0.00 |
| 0 nos | Ventilator in rooms | Rs. 65,000.00 | 0.00% | Rs. 0.00 |
| Sub Total | Rs. 74,300,000.00 |
| Tax | Rs. 0.00 |
| Total | Rs. 74,300,000.00 |