1st Floor, Noor Square, Opp. Askari Park, Old Sabzi Mandi, Karachi
Quote Number | QUO-647 |
Quote Date | May 19, 2025 |
Total | Rs. 32,800,500.00 |
-
-
Replacement of roof in internal work 8500 sqft
Hrs/Qty | Service | Rate/Price | Adjust | Sub Total |
---|---|---|---|---|
1 Job | Demolishing the existing damage roof slab & removal of debris out of side |
Rs. 450,000.00 | 0.00% | Rs. 450,000.00 |
15 ton | Providing & binding iron steel D form (Agha / nagina) of appropriate size as per existing beams & columns ( existing beam & column will be used ) |
Rs. 290,000.00 | 0.00% | Rs. 4,350,000.00 |
4250 cft | Cost of labor & material for pouring the roof slab 1:2:4 ration cement concrete in SR cement including Shutring, pouring & curing. |
Rs. 2,400.00 | 0.00% | Rs. 10,200,000.00 |
1 Job | New Block masonry for Damage walls |
Rs. 936,000.00 | 0.00% | Rs. 936,000.00 |
1 job | Plaster from inside & outside on new block masonry in 1:4 ratio cement concrete. |
Rs. 1,872,000.00 | 0.00% | Rs. 1,872,000.00 |
1 job | Plaster the roof from inside 1:4 ratio CC motor including bonding agent for maximum strength |
Rs. 1,912,500.00 | 0.00% | Rs. 1,912,500.00 |
1 Job | Spreading the Cementous water proofing (Saika / Recochem ) |
Rs. 680,000.00 | 0.00% | Rs. 680,000.00 |
1 Job | Providing & fixing the marble above the roof slab (tervera) |
Rs. 1,530,000.00 | 0.00% | Rs. 1,530,000.00 |
1 job | Cost of concealed electrical piping / wiring for lights & fans in million cable |
Rs. 987,000.00 | 0.00% | Rs. 987,000.00 |
27 nos | Replacement of UPVC window |
Rs. 38,000.00 | 0.00% | Rs. 1,026,000.00 |
27 nos | Providing & fixing UPVC doors with frame |
Rs. 47,000.00 | 0.00% | Rs. 1,269,000.00 |
1 Job | Providing & laying marble in classrooms (virona) |
Rs. 1,475,000.00 | 0.00% | Rs. 1,475,000.00 |
1 Job | Providing paint in side the building in vinyl emulsion & oil paint boarder upto 4ft |
Rs. 978,000.00 | 0.00% | Rs. 978,000.00 |
1 Job | Supply & fixing inverter fan 4 fan & lights in each classroom (40 fans & 30 tube light) with switch sockets |
Rs. 1,150,000.00 | 0.00% | Rs. 1,150,000.00 |
1 Job | Providing & laying of stone outside the existing building (Gadap yellow / red ) |
Rs. 3,435,000.00 | 0.00% | Rs. 3,435,000.00 |
1 Job | Renovation of inside washroom | Rs. 550,000.00 | 0.00% | Rs. 550,000.00 |
Sub Total | Rs. 32,800,500.00 |
Tax | Rs. 0.00 |
Total | Rs. 32,800,500.00 |