1 Job |
Laying floor tiles in 2 rooms & hall complete.
|
Rs. 281,200.00 | 0.00% | Rs. 281,200.00 |
1520 Sqf |
Cost of Floor tiles 4x2 with dry bond
|
Rs. 261.00 | 0.00% | Rs. 396,720.00 |
3 nos |
Providing & laying of tiles in washroom walls & floor with dry bond on walls & cement motor on floor
|
Rs. 219,625.00 | 0.00% | Rs. 658,875.00 |
2 nos |
Cost of Labor Charges for laying of concealed fresh water & drain line, fixing of new taps & ceramic (Labor only)
|
Rs. 35,000.00 | 0.00% | Rs. 70,000.00 |
1 |
Cost of removal & fixing of new taps & ceramic
|
Rs. 15,000.00 | 0.00% | Rs. 15,000.00 |
2 nos |
Cost of plumbing material PVC pipes & fittings 3/4" dia for fresh water & 4" dia pipe for drain lines & 3" for wash basin drain.
|
Rs. 69,000.00 | 0.00% | Rs. 138,000.00 |
3 nos |
Cost of sanitary ware & accessories.
|
Rs. 87,400.00 | 0.00% | Rs. 262,200.00 |
3 nos |
Providing & making vanity in all 3 washrooms
|
Rs. 42,300.00 | 0.00% | Rs. 126,900.00 |
1 job |
Providing and making flowerbed outside boundary wall
|
Rs. 65,000.00 | 0.00% | Rs. 65,000.00 |
1 Job |
Faucet for 1 washroom only
|
Rs. 45,000.00 | 0.00% | Rs. 45,000.00 |
1 Job |
Providing & Water Proofing (2 Coats) after applying of plugging chemical where required, after making the surface rough & cleaning before application
|
Rs. 329,612.00 | 0.00% | Rs. 329,612.00 |
1 Job |
Providing & fixing Main glass double door with handle & frost paper |
Rs. 44,000.00 | 0.00% | Rs. 44,000.00 |