OT Complex | Ramp Tile

Hrs/Qty Service Rate/PriceAdjustSub Total
1797 Sqf Providing & laying anti skit tile (size 16 x 16) on Ramp with dry bond on existing floor & slope, cost include labor, material & cartage

170 mtr tiles @ 1600/- 272000/-
150 bags Original sea star Bonds 550/- 82500/-
3 bag Grout 1250/- 3750/-
1797 Sqft labor @ 50/- 89850/-
3 trips Cartage @ 4500/- 13500/-
Total : 461600

Rs. 256.870.00%Rs. 461,599.99
1 Job Cost of labor charges for closing drain channel & making new drain points for water disposal
Rs. 18,000.000.00%Rs. 18,000.00
1110 Sqf Providing & fixing of tile on side wall of OT ramp with dry bond
Rs. 256.000.00%Rs. 284,160.00
1 Job Cost of labor charges for chiseling of plaster from walls & throw the debris out of side
Rs. 22,500.000.00%Rs. 22,500.00
1 job Profit Rs. 141,526.000.00%Rs. 141,526.00
Sub Total Rs. 927,785.99
Tax Rs. 0.00
Total Rs. 927,785.99