Quote

From:

1st Floor, Noor Square, Opp. Askari Park, Old Sabzi Mandi, Karachi

Quote Number QUO-116
Quote Date December 20, 2022
Total Rs. 787,200.00
To:
Private

Mr Kamil | Water Proofing at Roof Top

Hrs/Qty Service Rate/PriceAdjustSub Total
1 Job Removal of damage flooring & pipe foundations, repair the same with 1:4 CC ratio including Rubber concrete chemical for maximum strength
Rs. 36,000.000.00%Rs. 36,000.00
1 Job Providing & making Cementitious 2 component water proofing after complete cleaning on roof
Rs. 418,200.000.00%Rs. 418,200.00
4 nos Widening the drain outlets
Rs. 1,800.000.00%Rs. 7,200.00
1 Job Cost of labor & material for cracks repairing in outer wall after widening the crack & fixing of wire mesh.
Rs. 87,000.000.00%Rs. 87,000.00
1 job Cost of labour and material for making CC gola on all corners and edges at roof top
Rs. 43,000.000.00%Rs. 43,000.00
1 job Providing & repairing all the chajjas including the floor on top of all chajjas in proper sloping & repairing from sides & bottom as discuss
Rs. 168,000.000.00%Rs. 168,000.00
1 job Replacing of damage drain pipe from 1st floor to ground floor on the left side area & laying of PVC pipe for all Air conditions drain water to prevent the wall & chajjas from further damages. Rs. 27,800.000.00%Rs. 27,800.00
Sub Total Rs. 787,200.00