Basketball Court - College Section
Hrs/Qty | Service | Rate/Price | Adjust | Sub Total |
---|---|---|---|---|
1 Job | "The Construction area must cordoned off in this Manner that inside working area not seen drom outside from two sides with heavy green net and safekeeping of all material should be provided within the cordoned-ff construction area. Approx. running length : 215 RFT (All material used for cordoned-ff will be client's property after completion of work)" |
Rs. 80,000.00 | 0.00% | Rs. 80,000.00 |
3000 Sqf | Removing of existing loose floor manually with care approx. minimum depth 2" to 3" , expose steel bars where possible including apply anti rust on exposed rusted steel bars after removal of rust using steel wire brush, shifting of debris through trucks from site and concreting of same area using concrete rato 1:2:4 and put new steel from where steel will be removed during cutting of concrete. |
Rs. 265.00 | 0.00% | Rs. 795,000.00 |
1 job | Filling of cracks with sand cement mortar mixed with bonding agent buza 16/123 for strenghth. Minor cracks to be filled with filler zahabiya soft seal special ZSP-1191 |
Rs. 75,000.00 | 0.00% | Rs. 75,000.00 |
700 Sqft | Providing & applying cement finish plaster 1:4, minimum 1/2" or 3/4" thickness including using zuba 16/123 and excavation, chipping or chiesling of plaster where required complete. |
Rs. 125.00 | 0.00% | Rs. 87,500.00 |
165 Rft | Construction of RCC Drain in U-Shape using 1:2:4 concrete ratio as per sketch approx. size 165' length (Garden and Cricket pitch side), 2'-0" wide x 1'-6" deep (inside finish size 12" wide x 10" deep at strting point) including excavation as per drawing and site requirment, 2'-6" wide and 4" thick 1:3:6, 2'-6" wide and 12" thick stone soling on compacted earth, water tight shuttering, use 3/4" dia bar @ 10" c/c in U-shape drain ( floor with proper chamfering between floor and wall joint and 2 side walls from inside and one wall from outside ) using 1:4 ratio and Zuba 16/123, drain grating consist of 1.5" x 1.5" x 1.5" angle embeded in concrete, top grating of 1.5" x 1.5" 1.5" angle wielded with vertically flat patti 1.5" x 1.5" at 1" apart, painting of MS grating with one coat of red oxide and three coat of namel paint of ICI / BERGER of approved color shade, applying of 3 coats of Zahabiya water shield on uter side wall of drain complete. Contractor must maintain proper slope as per site requirment and drain must be waterproof. |
Rs. 4,250.00 | 0.00% | Rs. 701,250.00 |
1 no | Providing and Laying 8" thick block masonry with plaster (inside and outside) for manhole approx. size 2'x2'x2'-6" (inner size) or depth as per site requirment for drain piping including excavation, backfilling with compaction, cast iron heavy duty manhole cover with painting, waterproofing of manhole ( inside and outside) , fixing of 3 nos. PVC pipe of 4" dia AGM make closing system ( Contractor must see sample before quote) from manhole to road nala side including cutting of beam and kerb stone for laying of pipes, removing and refixing of pavers, khaka base concrete after layong of pipes with proper finish, as directed by school management complete. |
Rs. 65,000.00 | 0.00% | Rs. 65,000.00 |
2 no | Providing and Laying 8" thick block masonry with plaster (inside and outside) for manhole approx. size 2'x2'x2'-0" (inner size) or depth as per site requirment for drain piping including excavation, backfilling with compaction, cast iron heavy duty manhol cover with painting, waterproofing of manhole (inside and outside), as directed by school managment complete. |
Rs. 80,000.00 | 0.00% | Rs. 160,000.00 |
150 Rft | Providing and laying of 6" dia PVC Pipe of AGM Make including elbows, sockets etc between two drains and manhole to manhole from basketball court to servant bloack main drain including excavation, backfiling after laying of pvc pipe including dressing, compaction, cutting of holes in manholes to insert pipes and finish after cutting, provide proper stable base below pipes along the length and maintain proper slope, removal of pavers, base concrete and stone soling and finish the same after laying of pipe in servant block area as per site requirment complete in all respect |
Rs. 650.00 | 0.00% | Rs. 97,500.00 |
6000 Sqf | Providing and laying of polypropylene interlocking tiles size 1'x1'x13.5 mm thick on basketball court of approved color (tiles will be layed in color combination as approved by school management) including marking of court and KGS LOGO as per manufacturer recommendation complete. | Rs. 0.00 | 0.00% | Rs. 0.00 |
Sub Total | Rs. 2,061,250.00 |
Tax | Rs. 206,125.00 |
Total | Rs. 2,267,375.00 |