1st Floor, Noor Square, Opp. Askari Park, Old Sabzi Mandi, Karachi
Quote Number | QUO-300 |
Quote Date | June 12, 2024 |
Total | Rs. 114,000.00 |
-
Front Column Concrete
Hrs/Qty | Service | Rate/Price | Adjust | Sub Total |
---|---|---|---|---|
2 nos | Cost of jacketing of front column on front entrance after necessary chiseling of plaster & removal of lose concrete including application of anti-rust chemical on exposed iron, addition of new iron bars & pouring the 1:2:4 concrete adding rubber concrete bonding agent with plaster finish. Cost also include block messonary UpTo top beam and plaster the same in rectangle shape | Rs. 57,000.00 | 0.00% | Rs. 114,000.00 |
Sub Total | Rs. 114,000.00 |
Tax | Rs. 0.00 |
Total | Rs. 114,000.00 |